Operations updates

Electrical shutdowns over winter break
A scheduled electrical shutdown for the campus will occur during the Winter Break time. This scheduled shutdown is part of the pre-construction phase prior to the construction of new School of Education and the Science Connector Building.The electrical shutdowns will be on Dec. 28 and Dec. 29. The work will begin at approximately 7:30 a.m. each morning. The following is a list of the affected buildings:

  • Dec. 28: The electrical shutdown will affect The Knapp Center, Fieldhouse, Bell Center, Shivers, and the Greenhouse. The power outage will last approximately 12 hours. Once this work is completed, the power will not be reconnected to the Greenhouse.
  • Dec. 29: The electrical shutdown will affect Jewett Hall, Olin Hall, and Cartwright Hall. The power outage will be approximately two to four hours.

The communication duct work will be completed on Dec. 30 and Dec. 31. This may interrupt telephone and Internet services to Olin, Fitch, Harvey Ingham, Medbury, and Cline halls; Facility Services; Environmental Health & Safety; the Fieldhouse; and Bell Center. DTS will be sending out more information on the communication duct work next week.

—Submitted by Jolene Schmidt, Director of Operations & Support Services

 

Building hours and access over break
Door schedules will change for the holiday break. We will adopt “administrative hours” for most of the buildings following commencement. Buildings will be open on weekdays from 7:30 a.m. to 4:30 p.m. Dec. 21–23. Doors will then be locked for the holiday break from Dec. 24 to Jan. 3.

Faculty and staff will still be able to utilize their authorized access plans (for example, 24/7 access to their office buildings), but student plans will be shut off during this time. Regular building hours will resume at the start of January Term, Jan. 4.

Please contact Public Safety (515-271-2222) if you have a door access emergency during this time, or contact the Student Services Center (515-271-2000 or studentservices@drake.edu) if you have a general card access question or concern.

Happy Holidays!

—Submitted by Sara Heijerman, Manager, Campus Card Office


Construction Update

27th Street will stay open until construction starts on the new School of Education. 27th Street usage will change once construction starts. Please read OnCampus in late January/early February for more information regarding the usage of this street.

—Submitted by Jolene Schmidt, Director of Operations & Support Services