A scheduled electrical shutdown for the campus will occur during the Winter Break time. This scheduled shutdown is part of the pre-construction phase prior to the construction of new School of Education and the Science Connector Building.The electrical shutdowns will be on Dec. 28 and Dec. 29. The work will begin at approximately 7:30 a.m. each morning. The following is a list of the affected buildings:

  • Dec. 28: The electrical shutdown will affect The Knapp Center, Fieldhouse, Bell Center, Shivers, and the Greenhouse. The power outage will last approximately 12 hours. Once this work is completed, the power will not be reconnected to the Greenhouse.
  • Dec. 29: The electrical shutdown will affect Jewett Hall, Olin Hall, and Cartwright Hall. The power outage will be approximately two to four hours.

The communication duct work will be completed on Dec. 30 and Dec. 31. This may interrupt telephone and Internet services to Olin, Fitch, Harvey Ingham, Medbury, and Cline halls; Facility Services; Environmental Health & Safety; the Fieldhouse; and Bell Center. DTS will be sending out more information on the communication duct work next week.

—Submitted by Jolene Schmidt, Director of Operations & Support Services