The pre-construction project to move an electrical distribution line and to move a communication duct is nearly complete; this project needed to be completed prior to construction of the new Science Connector Building and the new School of Education. A portion of sidewalk is currently closed on the west side of 27th Street, just east of Medbury Hall. This sidewalk should be poured early next week. The project is approximately two weeks ahead of schedule. The construction will continue for the next week or two in a grassy area between Medbury and Jewett Hall parking lot, but will not close any sidewalk.
—Submitted by Jolene Schmidt, Director, Operations and Support Services