Network Refresh Project Underway

Earlier this month ITS officially kicked off the planned multi-year network refresh project. This project aims to replace all wireless access points and network switches on campus over the next three years. This work is essential as we work to support growing connectivity needs, plan for future wireless technologies, and maintain a secure campus network.

The project will be completed in two major phases. The first will be focused on replacing wireless access points across campus with the second phase being focused on replacing network switches.  While most of the new access points will replace existing older equipment, the team is working hard to identify areas where additional wireless coverage is needed and ensuring the resources are being leveraged in the best way possible. 

Below is the tentative planned roll out of the wireless access points across campus. Please note that these building groups and dates can change based on hardware availability and building event schedules. 

Building TypeProjected Implementation
Athletic BuildingsFall 2025
Group 1 Administrative BuildingsFall 2025
Group 1 Academic BuildingsJ-Term 2026 / Spring 2026
Group 2 Administrative BuildingsSpring 2026
Residence HallsSummer 2026
Group 2 Academic BuildingsFall 2026 / J-Term 2027

We understand that stable and reliable internet access is critical to teaching, learning, and daily campus operations. To help ensure minimal campus impact, we will be reaching out to building managers prior to the start of work in their assigned building. We will notify them of projected start dates as well as identify any additional events or activities happening in that area.

For more information about the project and to see ongoing building status updates, please visit our project internal site. 

Network Refresh Project Internal Site 

— Jeff Regan, ITS